Independent Surveillance Assessment of Pre-Installation Building Inspections

In 2024 ATMA received a Scope Extension from TrustMark to enable it to offer an additional workstream to its members.

In addition to ATMA members being registered under the trade code ‘Retrofit Energy Efficiency Inspectors’ members can also extend scope to offer Independent Surveillance Assessment of Pre-Installation Building Inspections.

Some of ATMA’s members already offers an independents PIBI checking service and this now formalises the offering and adds a level of auditing and accountability to the process with traceability on who carried out individual checks and the outcome.

Why is this necessary?

The requirement for independent verification of the findings of the Pre-Installation Building Inspection was introduced back in 2014 for Cavity Wall Insulation (CWI).

This has since been extended over the PAS revisions to cover Room in Roof Insulation (RIRI), Internal Wall Insulation (IWI) and following the 2023 amendments to PAS 2030 there is now a requirement to demonstrate that independent checks have been undertaken for all insulation measures claiming compliance with PAS 2030.

These checks are a combination of desktop assessments and on-site assessments to ensure that the building is suitable to receive the measure and that the proposed system and design meets the PAS requirements. The requirements are set out in the
relevant PAS 2030 Measure Annex.

The introduction of these checks has proven to reduce installer and design errors and improve post installation compliance and customer satisfaction, reducing the need for property revisits and the associated remedial costs.

How will the scheme operate?

Members accepted onto the scheme will undertake checks on the Pre-Installation Building Inspection and other associated documents such as the Retrofit Design to ensure completeness and accuracy and that the proposed measure(s) are suitable for the property.

The scheme will initially cover the following measures:

  • Cavity wall Insulation
  • Loft Insulation
  • Internal Wall Insulation
  • External Wall Insulation
  • Underfloor Insulation
  • Flat Roof Insulation
  • Pitched Roof Insulation
  • Room in Roof Insulation

Each successful check will be allocated a coded Unique Assessment Reference (UAR) which will identify to ATMA the company undertaking the check, installer, property and measure subject to surveillance.

This UAR is critical element to allow verification by ATMA, TrustMark and other third parties such as System Designer s or warranty providers. The UAR’s produced by each member will be shared with ATMA on a monthly basis.

How will the scheme be monitored and managed?

An application process and auditing regime has been agreed with TrustMark.

Members of the scheme must be able to demonstrate independence from the supply chain and must adhere to the Scheme Rules and issued Codes of Conduct.

ATMA will audit a percentage of audits undertaken by each member with the determined by previous audit outcomes.

Sanctions (including suspension or removal from the scheme) are in place for members who repeatedly breach the Scheme Rules or are not able to demonstrate that changes have been made to prevent reoccurrence.

How do I become a member of the scheme?

Initially the scheme is open to existing ATMA members who can apply for a scope extension following application and audit. Membership will then open up later in 2025 for new members who aren’t currently core members of ATMA but wish to join to undertake this activity under a TrustMark registered scheme.

If you are not currently a member of ATMA and wish to register your interest so that you can be contacted when applications open up please email: admin@atma.ltd

To be accepted onto the scheme the applicant must be able to demonstrate that they are not involved in the installation of energy efficiency measures and that they are independent from the companies that they offer the service too. They must also be able to demonstrate auditor and organisational competency and that a robust set of processes are in place. They must report all completed checks to ATMA for surveillance and commit to adhere by the Scheme Rules and Code of Conduct.